Welcome to Swet Ganga Hydropower & Construction Limited

Key dates of the Project

Title Date
Generation License issued by Department Electricity Development (DoED), Ministry of Energy (MoEn), Government of Nepal (GoN).
The license period of the project is from 28 Chaitra 2072 to 27 Chaitra 2107 B. S. [1st Amendment on 10 Chaitra 2077]
2 Baisakh 2073 (14 April 2016)
Power Purchase Agreement (PPA) with Nepal Electricity Authority (NEA) 14 Poush 2073 (29 December 2016)
Financial Closure 10 Falgun 2074 (22 February 2018)
Contract of Main Civil Works  5 Chaitra 2074 (19 March 2018)
Contract of Hydro-mechanical Works  9 Poush 2075 (24 December 2018)
Contract of Electro-mechanical Works   18 Bhadra 2076 (4 September 2019)
Contract of Transmission Line Works  8 Shrawan 2077 (23July 2020)
RCOD 15 Mangsir 2078 (1 December 2021)

Construction Management

The Employer/Owner

Swet Ganga Hydropower & Construction Ltd.

The Engineer/ Consultant 

Sanima Hydro and Engineering Pvt. Ltd.

The Contractor (Civil Construction Works) 

High Himalaya Hydro-Bavari Construction J.V.

The Contractor (Hydro-mechanical Works) 

 Machhapuchhre Metal & Machinery Works (P.) Ltd

The Contractor (Electro-mechanical Works) 

Asia Pacific Power-Tech Co. Ltd., China

The Contractor (Transmission-line Works) 

Aster Teleservices Nepal Pvt. Ltd.